Decommissioning a wind turbine does not include removing the massive concrete foundation blocks buried as deep as 15 feet into the ground, or cables buried deeper than 4 feet. Were it not for massive government subsidies, tax rebates and tax credits, no wind turbine would ever be erected. The cost of removal will not be born by the developer, but rather by the city or county. ⁃ TN Editor

********

ISAAC ORR

It looks like Minnesota will have a very expensive mess to clean up when the wind turbines currently operating in the state reach the end of their 20-year useful lifetimes.

According to utility documents filed by Xcel Energy for its Nobles Wind facility, it will cost approximately $445,000 (in 2009 dollars) per turbine to decommission the wind facility. This means it would cost $532,000 per turbine (in 2019 dollars) for each of the 134 turbines in operation at this facility, bringing the total cost of decommissioning the Nobles project to $71 million. However, Xcel also stated these estimates were conservative, meaning this likely represents the high-end cost of decommissioning.

Other wind turbines have six-figure decommissioning costs, as well. According to utility documents for the Palmer’s Creek Wind facility in Chippewa County, Minnesota, it would cost $7,385,822 to decommission the 18 wind turbines operating at that site, a cost of $410,000 per turbine.

One would think such a price tag would at least result in a thorough decommissioning job, but one would be wrong.

According to the Nobles Wind document, “Restoration activities will include and not be limited to removal of all physical material and equipment related to the project to a depth of 48 inches.”

This means Xcel will only remediate the site to a depth of four feet, leaving most of the massive concrete foundations, which go as deep as 15 feet, used to anchor the wind turbines, in the ground indefinitely.

Furthermore, according to the website, Nobles Wind facility has an extensive underground collector cable system, laid at a depth of four feet, connecting the turbines to a central substation. Xcel’s documents were not specific enough to determine if they would be removing these cables, but the Palmer’s Wind Farm project explicitly states that cables deeper than 4 feet would not be removed.

Read full story here…

************

Original article

••••

The Liberty Beacon Project is now expanding at a near exponential rate, and for this we are grateful and excited! But we must also be practical. For 7 years we have not asked for any donations, and have built this project with our own funds as we grew. We are now experiencing ever increasing growing pains due to the large number of websites and projects we represent. So we have just installed donation buttons on our websites and ask that you consider this when you visit them. Nothing is too small. We thank you for all your support and your considerations … (TLB)

••••

Comment Policy: As a privately owned web site, we reserve the right to remove comments that contain spam, advertising, vulgarity, threats of violence, racism, or personal/abusive attacks on other users. This also applies to trolling, the use of more than one alias, or just intentional mischief. Enforcement of this policy is at the discretion of this websites administrators. Repeat offenders may be blocked or permanently banned without prior warning.

••••

Disclaimer: TLB websites contain copyrighted material the use of which has not always been specifically authorized by the copyright owner. We are making such material available to our readers under the provisions of “fair use” in an effort to advance a better understanding of political, health, economic and social issues. The material on this site is distributed without profit to those who have expressed a prior interest in receiving it for research and educational purposes. If you wish to use copyrighted material for purposes other than “fair use” you must request permission from the copyright owner.

••••

Disclaimer: The information and opinions shared are for informational purposes only including, but not limited to, text, graphics, images and other material are not intended as medical advice or instruction. Nothing mentioned is intended to be a substitute for professional medical advice, diagnosis or treatment.